Tower A- 2nd Floor Slab completed in June 2013, Shuttering for 3rd Floor Slab in progress
Tower A- 2/3rd, 3rd Floor Slab casted in June 2013
Tower A- 3rd Floor Slab casted in June 2013
Tower A- Curing of 3rd Floor Slab in progress.
Tower B- Preparation for the 3rd floor slab in process. 1st pour scheduled for August 2013
Tower B- Steel reinforcement and shuttering in place for the first pour of 3d floor slab of Tower B.
Tower B- Shuttering in place for the final concrete pour of 3rd floor slab of Tower B (September 2013)