Tower A- Concrete of shear walls and columns for 2nd Floor slab completed in May 2013.
Tower A- shuttering being fixed for 2nd floor slab
Tower A- 1st pour of 2nd floor slab completed on May 30th, 2013.
Tower B-Preparation for casting of 1/3rd 2nd Floor slab- steel binding in progress
Tower B- 2nd floor slab completed in August 2013