Tower A- The shuttering for casting of 1st floor slab is in place.
Tower A- 2/3rd 1st floor slab casted. Completion of 1st floor slab in May 2013
Tower B- shuttering and steel in place for 1st Floor slab
Tower B- 1 portion of the 1st floor slab concreted on May 31st, 2013
Tower B- 1st Floor Slab completed June 2013